Connecting your solar installation to Senelec in Senegal: authorisations, procedures and surplus feed-in

The 2026 guide: self-consumption, grid injection, Senelec procedures, surplus sale. Reference texts and up-to-date processes.

15 November 2026 · By Cheikh Mohamed Dieye, Chief Executive Officer · Dieye Solar Group
1 MWc solar plant directly injected into the Senelec grid by DSG at Sandiara

Three ways to connect a solar installation in Senegal

In Senegal, three setups exist: off-grid (no link with Senelec, 100 % solar + batteries), self-consumption (solar supplies first, Senelec tops up), and injection (surplus sent to the grid). Administrative steps differ. An off-grid site needs no Senelec authorisation. Self-consumption and injection do.

Self-consumption without injection: what to do

This is 90 % of residential and commercial installations DSG delivers. You consume solar power when it is available and Senelec takes over the rest of the time. The battery stores surplus for the night. No surplus is returned to the grid. Procedure: a simple Senelec declaration with the installation diagram is enough in practice. The installation must meet IEC standards (differential protections, grounding, anti-islanding). No specific contract.

Surplus injection: the new regime

Since Law n° 2021-31 on the electricity sector and its implementing decrees, Senegal recognises the net metering principle (production injected offsets consumption). The CRSE (Electricity Sector Regulation Commission) and Senelec frame the conditions. To inject, you need: (1) a bidirectional meter provided by Senelec, (2) a certified inverter with anti-islanding, (3) a self-consumption contract with injection signed with Senelec, (4) compliance with CRSE power limits. Buyback tariffs are evolving; check with your local Senelec office.

Industrial direct injection: the 1 MWc model

For industrial projects from a few hundred kWc up, direct injection (no battery) is often the most profitable option. All energy produced is instantly consumed by the site, which reduces Senelec consumption by that amount. This is the model of DSG's 1 MWc Sandiara plant: 7 Sungrow 115 kW inverters, direct injection into the industrial panel, 100 % of the factory's daily needs covered without batteries. ROI is around 3 years versus 5 years with storage.

Authorisations and required documents

  • Senelec declaration: letter to the local office with single-line diagram and installed power.
  • IEC compliance certificate: issued by the installer (DSG does this for every project, with signed report).
  • Self-consumption contract (if injection): Senelec form + meter number + owner's ID copy.
  • Bidirectional meter: ordered from Senelec, installed within 2-6 weeks depending on office.
Larger projects (>500 kWc) also go through ANER and CRSE technical review.

Who does what in your project

At DSG, we handle the entire administrative file for our clients: Senelec letter, single-line diagram, compliance certificate, submission and follow-up with the office. Our 2025-2026 projects were all connected without disputes. We work regularly with the Senelec offices of Thiès, Dakar and Mbour.

Frequently asked questions

Do you need Senelec authorisation to install solar panels?
For a 100 % off-grid site (no Senelec link), none. For self-consumption without injection, a simple declaration to Senelec with the installation diagram is enough. For surplus injection, you need a self-consumption contract with injection and a bidirectional meter.
Can you sell your solar surplus in Senegal?
Yes, since Law n° 2021-31 on the electricity sector. Net metering is recognised: injected surplus offsets your grid consumption. Practical conditions (buyback tariff, procedure) are negotiated with Senelec via a self-consumption-with-injection contract.
What is anti-islanding and why is it mandatory?
Anti-islanding is a safety function that cuts the solar inverter if the Senelec grid fails. It prevents a solar installation from continuing to inject on a dead Senelec line, which would kill technicians working on it. All IEC 62116 certified inverters include this function.

Need a free study?

Let's talk about your project.

Free study within 72 hours, detailed line-by-line quote, on-site visit by our teams.